General Installation Steps
General Installation Steps
HOME » PRODUCTS » Slide Rail Shoring System » General Installation Steps
Easy Installation
- Complete system consists of four basic components: corner posts, spreader posts, panels, and spreader beams
- Entire system can be installed quickly and cost effectively using an excavator and a small crew
- Rolling spreader frame permits vertical movement of spreaders for greater access and maximum clearance
- Frame also helps keep posts parallel with each other and allows maximum advancement of components
- Smooth panels are easier to install and remove than stacked tube designs
4-sided pit installation
|
After initial excavation, first outer panel and corner post is put into place. |
Second panel and corner post forms a right angle. |
With outer panels and corner posts in position... |
excavation continues... |
|
while outer panels and corner posts are pushed to proper depth with excavator. |
Excavation is deepened and panels are lowered into inside tracks. |
Excavator continues to dig and push the inside panels and corner posts... |
until desired depth is reached. |
|
Removal begins by extracting inner panels as back filling and compaction is started |
Outer panels and corner posts are extracted as back filling and compaction is completed |